Client / Owner
|
Job Description
|
Location
|
Contract
|
| AJINOMOTO ENGINEERING (2001) CO., LTD. |
18.14 MB |
| Kamphaeng Phet Factory |
Lighitng & Receptacle Works at Husk Sotehouse |
|
|
|
Electrical & Instrument Works TM-E2 Project |
|
|
|
Installation E & I Work Project Evaporator N8 |
|
|
|
Lighting System Installation at Evaporator N4A |
|
|
|
Electrical Work For AC Tower Process at N4B |
|
|
|
Electrical Work of Moter Tepioca Ship Testing at H1 |
|
|
|
Installation Lighting System at Evaporator N4B |
|
|
|
Electrical & Instrument Work for Biomass Steam Header, WWT & AS System at Factory 1,2 and Biomass Process |
|
|
|
Riken ( Thailand )
|
Electrical & Instrument Works
Installation Power Plug Carry for Machine at Cooling Process
Install Push Button Switch Box for Vacuum Cleaner System at X5 Process And Cooling
|
Bangkadi I.E
|
|
| Ajinomoto NK BR-Project |
|
Nongkhae I.E |
|
|
Install Lighting Fixture Water Proof at Extractor Machine Area |
|
|
|
Electrical & Installation System for Utility |
|
|
|
Electrical & Installation System for Extractor Machine |
|
|
|
|
|
|
| CH.KARNCHANG PUBLIC CO.,LTD. |
99.43 MB |
| Southern Outer Bangkok Ring Road |
E&M Erection Work Main Contract |
Bangkhunthian,Suksawat |
|
LV.Distribution Power Supply & Canopy Lighting
Fresh Air Duct For Toll Canopy
Water Drain Piping Work For TOLL Plaza
Miscellaneous For Electrical And Mechanical Work
Install Floodlight 2x400W HPS.14M Post Top
Install Main Feeder Route & Conduit Work
Electrical Work for TSB Type C (Exit No.2,Exit No.4 )
E&M Work for Stair Tower ,Walk Way ,Cat Walk
C-Channel Support at Canopy Island ( Toll Canopy )
Electrical & Lighting System For Instant Building
|
|
|
| Southern Outer Bangkok Ring Road |
E&M Erection Work |
|
|
|
Electrical System ,Communication System , |
Bangkhunthian,Suksawat |
72.60 MB |
|
Plumbing System |
|
|
| FUJIDENKI ENGINEERING CO., LTD. |
23.20 MB |
| Siam Yamato Steel-2 Co.,Ltd |
Electrical Installation Work for Melt Shop,CCM,RHF & Utility System |
Maptaput Rayong |
|
| |
Electrical Work For Melt Shop ( Underground DCS)
Electrical InstalLationWork for Melt Shop (RMH,LF,EAF,DCS,CCM Area)
Electrical Work for Melt Shop ( Lighting System)
|
|
|
| Siam Nippon Steel Pipe Co.,Ltd (SNP) |
Electrical Installation Work For Machine |
Siam Eastern Ind.Park |
|
| |
Temporary Electrical Installation Work For Site Office |
|
|
| STP#2 EPL Project |
Electrical Installation Work For STP#2 EPL Project |
Maptaput,Rayong |
|
| |
Modify Copper Bus Bar (2) SET
Install Aircondition in Center Control Room
|
|
|
| AIT-2 Project |
Electrical Work for 2nd DE-BOTTLENECKING (AIT-2) |
Maptaput,Rayong |
|
|
Addition Electrical Work for 2nd DE-Bottlenecking |
|
|
| Thai Meira Factory |
Relocation Work for M/C at Factory 1,2 |
Siam Eastern Ind.Est |
|
|
Electrical Installation Work for Mainfeeder & No.4 Surface Reprement
Electrical Installation Work for Factory Phase 3,4,5
|
|
|
|
|
|
|
| MARUBENI CORPORATION |
|
|
|
| MARUBENI CORPORATION |
|
Songhla 99.23 MB |
| Electricity Generating Authority of Thailand (EGAT) |
Project : Songkhla Combined Cycle Power Plant Block I |
|
Supply and Install of Temporary Air Condition
Supply of Lighing & Small Power, HVAC & VAC Susytem
Erection & Commissioning for Lighing & Small Power, HVAC & VAC Susytem
Supply and Install Signal Alarm System
Spare Parts for Lighing & Small Power, HVAC & VAC System
|
| SIAM YAMATO STEEL CO., LTD. |
|
9.45 MB |
|
Secondary Grounding System For Machine at Rolling Mill BLDG |
Hemaraj Ind. Est.Rayong |
|
Underground Grounding System for Lighting Protection System at Rolling Mill |
|
|
|
Above Ground For Lighting Protection System at Rolling Mill |
|
|
|
Underground Grounding System for Lighting Protection System at Melt Shop |
|
|
|
Above Ground for Lighting Protection System at Melt Shop |
|
|
|
Above Ground for Lighting Projection System Canopy C05-C030 |
|
|
|
|
|
|
| SCI PLANT SERVICES CO.,LTD. |
|
12.08 MB |
| Siam Yamato Steel 2 Plant |
Machine Grounding for SYS-2 Steel Plant |
Hemaraj Ind. Est.Rayong |
|
Grounding for O2 GAS STATION
Secondary Grounding System For Machine at Rolling Mill Bldg
Installation Work For Primary Grounding Work
Installation Primary Machine Grounding Work For SYS-2 Steel Plant
|
|
|
| TOYO-THAI CORPORATION PUBLIC COMPANY LIMITED |
37.97 MB |
| PTTPE LDPE PROJECT |
Electrical Construction Work Main Contract |
Maptaput Rayong , Rayong |
| THAI TOKO ENGINEERING CO., LTD. |
106.20 MB |
| CMK ( Thailand ) New Factory |
Electrical & Communication Installation Works |
304 Industrial Park, Prachinburi |
|
Miscellaneous Work / General Addition Work
Maintenance Work @ Main Substation
Miscellaneous Work & Power Supply For Machines
Machine
|
|
|
| H-One Part |
Electrical Installation & Communication Works |
Rojana Industrial Park (Ayutthaya) |
|
Modify Existing Hight Voltage Incomming Phase 9 |
|
|
|
Dismantle Barbox Welding Machine PP-9/1,PP-9/3,PP-6/6 at Phase 5 |
|
|
Dismantle Barbox For Panel A (Fr.BHD) at Phase 2 |
|
|
|
Relocate Barbox Welding Machine PP-12/4 At Phase 9 |
|
|
| PCTT Ayutthaya -C1,C2C Factory |
Electrical & Comunication Work New Clean
|
Rojana Industrial Park (Ayutthaya) |
| |
Electrical & Comunication Work New ASSY-1~2 at C2C Factory
Power Supply Main Scrubber
Power Supply M/C G21-22 at PR-C101 RM
Main Power Supply Boiler & Control System
|
| LTEC LTD. (Lana Thai Electronic Components) |
Northern Region Industrial Estate, |
|
Renovation 1St FL. LTEC-2 |
Lamphun |
|
|
Second Floor Renovation For Painting Room |
|
|
|
Electrical Miscellaneous Addition Electrical Work LTEC # 2 Factory |
|
| Asean B-CAR ( AAT ) Project |
Conduit Piping Work For Fiber Optic Cable In Cutter |
Eastern Seaboard Ind. Rayong |
| |
Relocation Lighting ( Hi Bay ) For Existing Body Shop 1
Main Power Supply Electrical Work at Asean B-CAR (AAT)
|
|
|
| Asean B-Car Body Shop 1 |
Electrical Construction Works for Body Shop 1 Expansion |
Eastern Seaboard Ind. |
|
| Expansion |
Electrical Construction Works |
Rayong |
|
| |
Install Welding Box at Stamping Shop 1 Explosion Proof |
|
|
| Thai Meira Co.,Ltd |
Electrical Construction Work for New Factory Phase 5 |
Amata Nakorn Ind |
|
| San-Ei Factory |
Electrical Installation & Communication Works |
Amata Nakorn Ind |
|
| ARST Factory |
Electrical Installation Work for Assembly Room |
Amata Nakorn Ind |
|
|
Main Power Supply Work for Crane 20T Line K-28 |
|
|
|
Relocation Work for PP-207 Panel |
|
|
|
Relocation Work for PP-1-1,PP-1-2,LP-133-02,LP-133-03 Panel |
|
| MCP Factory |
Renovation Lighting Sytem Work for Factory 1 |
Amata Nakorn Ind |
|
| |
Modify Lighing Work ofr 2FL Factory 1
Change Lighting Fixture Work for Factory 1
Lighting System Work Near New Car Park
Communication System Installation Work for F1 & F2 (Monitoring Alarm)
Lighting System For Mold-Die
|
|
|
| Toyota Factory (TMT) |
Electrical Renovation Work for Office Building |
Samrong Samutprakarn |
|
|
Lighting System For Fence at V/C YARD |
|
|
|
Overhaul & Repair Lighting System (High Mast Pole ) |
|
|
|
Temporary Main Feeder Supply Work |
|
|
|
Renovation Work For Head Office 1,Head Office 2 |
|
|
|
Renovation Work for Factory Office -3 Building |
|
|
|
Miscellaneous & Maintenance Works |
All Area 10.00 MB |
|
SUMMARY - 2008
|
488.30 MB
|